All resources

Contract terms for bidders: JYSE 2025, JIT, and YSE

Comprehensive guide to public procurement contract terms from the bidder's perspective. Identify risks, understand liability caps, and know when to negotiate.

KEY TAKEAWAYS

  • JYSE 2025 raised the maximum liability to 5x the contract value — for a one-million-euro contract, the liability cap is €5,000,000
  • Liquidated damages are typically 0.5–1% per week, capped at 10% of the contract value, and accrue automatically without a separate notice of breach
  • JIT 2015 includes an SLA penalty cap of 10–15% of the monthly fee, whereas JYSE has no separate SLA mechanism
  • Under YSE 1998 for construction contracts, the warranty period is 2 years and latent defect liability extends to 10 years, with a 10% performance bond during construction
  • The Q&A phase of the RFP is practically the only opportunity to request changes to contract terms — after submitting your bid, there is no room for negotiation

1JYSE 2025 — general contract terms in a nutshell

JYSE (General Terms and Conditions for Public Procurement) are standard terms published by the Finnish Ministry of Finance, used in the vast majority of public tenders. The 2025 update introduces significant changes that every bidder must understand before submitting a bid. JYSE comes in two versions: Services and Goods.

Understanding the order of precedence of contract documents is critical: the procurement contract takes priority, followed by the request for proposals and its appendices, the JYSE terms, and finally the bid. This means the contracting authority can deviate from JYSE toward stricter terms in the RFP, and these special conditions override JYSE.

The four most significant changes in JYSE 2025 are: raising the maximum liability to five times the contract value, a new competition restriction chapter, updated price adjustment terms (index clauses and duty to cooperate), and stricter subcontracting oversight.

For bidders, it is essential to compare the RFP terms against JYSE's standard terms. Every deviation toward stricter conditions is a potential risk that must be identified and priced into the bid.


2Liability — the most critical change in JYSE 2025

JYSE 2025 sets the maximum liability at five times the estimated value of the procurement contract. In practice, for a €100,000 contract the liability cap is €500,000, for a €500,000 contract it is €2,500,000, and for a one-million-euro contract it reaches €5,000,000. This is a significant increase compared to the previous JYSE 2014.

As a general rule, only direct damages are compensable. Indirect damages become compensable only in cases of intentional misconduct or gross negligence. This limitation is an important safeguard for bidders, but the threshold for gross negligence may be lower than many assume.

Before submitting a bid, the bidder must calculate the maximum liability and compare it to their own liability insurance coverage. If the liability cap exceeds the insurance limit, the bidder must either increase their insurance coverage, price the risk into the bid, or consider not bidding.

During the Q&A phase, it is always worth requesting a reduction of the liability cap if the maximum amount is disproportionate to the contract margin. Support your request with concrete numbers: 'The 5x liability cap is €2.5M, while the contract margin is approximately €50,000. We request limiting the maximum liability to the contract value.'


3Prices, delays, and sanctions

Under JYSE 2025, the default is that prices are fixed for the entire contract period, with no index adjustments unless separately agreed. In long contracts exceeding three years, this means the bidder bears the inflation risk alone. However, JYSE 2025 has clarified index clauses and introduced a duty to cooperate, meaning both parties must engage constructively in price adjustment negotiations.

Liquidated damages for services are typically 0.5–1% per week, capped at 10% of the contract value. For goods, the penalty is similarly percentage-based. Critically, liquidated damages accrue automatically without a separate notice of breach, and penalties accumulate up to the maximum cap.

Force majeure releases the supplier from liquidated damages, but the burden of proof lies with the supplier. In practice, this means the supplier must demonstrate the direct impact of the force majeure event on delivery and that the event could not reasonably have been foreseen or its effects avoided.

In long-term contracts, bidders should insist on an index clause. If the contracting authority does not accept one, the inflation risk must be priced directly into the bid. Price adjustments always require a written agreement — verbal agreements are insufficient.


4Intellectual property rights and confidentiality

The default position under JYSE 2025 Services is that the buyer receives a right of use to the deliverables, but copyright remains with the supplier. Background IP — the supplier's pre-existing know-how and tools — remains firmly with the supplier. This is a favorable starting point for bidders and worth defending.

However, the RFP may deviate from JYSE and require full transfer of IP rights to the buyer. This means the supplier cannot leverage the work results for other clients. Such a clause can be commercially devastating, particularly for software and consulting companies that reuse the same foundation across multiple clients.

If the contracting authority requires IP transfer, the bidder should price the rights transfer separately and clearly. Alternatives to propose include a broad license of use without ownership transfer, or transferring rights only for the customized components.

The confidentiality obligation is mutual and covers confidential information. It is effective during the contract and typically for 3–5 years after termination. The new competition restriction chapter in JYSE 2025 also introduces a cartel prohibition, conflict of interest rules, and an obligation to disclose potential competition restriction situations.


5JIT 2015 — special terms for IT procurement

JIT (General Terms and Conditions for IT Procurement in Public Administration) are IT-specific terms drafted by Hansel that supplement or replace JYSE in IT procurements. JIT consists of general terms (JIT 2015 General Terms) and appendix terms, from which the relevant ones are selected: JIT Services, JIT Consulting, JIT Managed Services, or JIT Software.

JIT differs from JYSE particularly in its SLA mechanism, data protection, and IP provisions. JIT includes a Service Level Agreement (SLA) where service levels, metrics, and penalties are defined. The penalty cap is typically 10–15% of the monthly fee. Data protection is GDPR-integrated, and security requirements may include Katakri or ISO 27001 compliance, as well as audit rights for the buyer.

Specific risks for IT suppliers include requirements specification risks (unclear or evolving requirements), integration risks (interfaces with other systems), fixed-price risk in development projects, and source code escrow requirements. The allocation of IP rights for customized software is always a matter of negotiation.

For bidders, JIT contract SLA terms must be analyzed carefully: are the service levels realistic, how is measurement conducted, and what is the cumulative impact of penalties on an annual basis? If the penalty cap is 15% of the monthly fee and service level breaches are ongoing, the annual revenue impact can be significant.


6YSE 1998 — general conditions for construction contracts

YSE (General Conditions for Building Contracts) 1998 are the standard terms for construction contracts. Dating from 1998, they are still widely used in public construction procurement. YSE imposes significant obligations on the contractor: the warranty period is 2 years from the acceptance inspection, and liability for latent defects extends up to 10 years.

Liquidated damages for construction contracts are 0.05% per working day, capped at 50 working days, totaling 2.5% of the contract sum. Performance bond requirements are 10% during construction and 2% during the warranty period. These tie up significant capital, and bonding capacity must be verified before bidding.

YSE clearly distinguishes between additional work and change orders. Change orders fall within the scope of the contract and the contractor must execute them, but additional work must be agreed upon separately. Critically, a written order must always be obtained for additional and change work before commencing — a verbal request does not protect the contractor in a dispute.

The contractor's strategy should be to price warranty period risks into the bid, ensure bonding capacity in advance, and meticulously document all additional and change work orders. Deficiencies at the acceptance inspection must be recorded precisely, as they determine the starting point of the warranty period.


7Contract terms risk analysis — checklist for bidders

Financial risks form the most critical part of contract terms. Always verify: the maximum liability relative to the contract margin, the magnitude and accumulation method of liquidated damages, the existence of a price adjustment mechanism (especially in contracts over 3 years), payment terms and schedule, and performance bond requirements and their capital impact.

Operational risks concern the day-to-day execution of the contract: the realism of SLA requirements, key personnel designation obligations, subcontracting restrictions, and the burden of reporting obligations. These risks do not directly translate to euros, but they can significantly increase the cost of contract execution.

Legal risks cover IP transfer, competition restrictions, scope and duration of confidentiality, applicable law (in international procurements), and grounds for contract termination. It is especially critical to identify whether the contract terms restrict your other business activities.

Each identified risk is assessed on a four-level scale: low (normal contractual risk, price if necessary), moderate (request clarification during the Q&A phase), high (evaluate go/no-go, request changes to the terms), and critical (disproportionate risk, request changes or do not bid).


8Can you request changes to contract terms?

In public procurement, room for negotiation is limited: the contracting authority generally cannot negotiate contract terms during or after the tender process. But this does not mean the bidder has no influence over the terms whatsoever.

The most effective channel is the Q&A phase of the RFP. Frame your question as a concrete proposal: 'We request considering limiting the liability to the contract value, as the 5x liability cap exceeds the market standard insurance coverage.' Always justify from the perspective of bidder risk and propose an alternative.

In a market dialogue, you can influence the terms before the RFP is published. In a negotiated procedure, negotiating contract terms is part of the process. In both cases, it is important to argue from the contracting authority's perspective: moderating disproportionate terms increases competition and lowers bid prices.

If the contract terms are unreasonable and the contracting authority does not amend them, the bidder must make an honest go/no-go decision. Do not bid if the liability significantly exceeds your insurance coverage, liquidated damages are disproportionate, IP transfer would destroy your business model, or a long-term contract lacks a price adjustment mechanism.


9Practical steps before submitting your bid

The first step is to identify which contract terms apply: JYSE 2025 Services, JYSE 2025 Goods, JIT 2015, or YSE 1998. Then review the RFP's special conditions, which take precedence over the standard terms. List every deviation from the standard terms and assess its impact.

Calculate the maximum liability in concrete terms: the estimated contract value multiplied by five. Compare this to your liability insurance limit and the estimated contract margin. If the liability cap is, for example, €2.5 million and the contract margin is €50,000, the risk-reward ratio is disproportionate.

Ensure that your subcontractor agreements include the same obligations and liabilities as the main contract. Under JYSE 2025, the supplier is responsible for its subcontractors as if for its own work, so a subcontractor's failure is directly your liability.

Actively use the RFP's Q&A phase. Ask about disproportionate terms, request clarification on ambiguous provisions, and propose concrete changes with justification. Document all questions and answers — they become part of the contract documents.

Haavi analyzes contract terms for you

Haavi automatically identifies risks in contract terms, compares them against JYSE standard terms, and calculates liability caps — so you can focus on bidding.

Ask Haavi

Chat with Haavi

Leave your details to start chatting with our AI assistant.